Permits · Virginia Beach, VA

Virginia Beach building permits: what needs one, how long it takes, how to check one

Most home projects in Virginia Beach need a permit, and most permits are quicker than people expect: on 61,407 residential applications the city published, the median wait from application to issue was 1 day. Structural work that needs drawings is the exception.

This page reads two records: the city's own application and issue dates, and 1,796 permits filed by contractors in BidBro's directory, sorted into 12 kinds of work with the value each was declared at. Together they answer what gets permitted, how long it takes and what it was worth.

BidBro Editorial Team·Published ·Updated

Key facts

  • Virginia Beach issued residential permit applications in a median of 1 day; nine in ten within 12 days (61,407 applications, January 2023 – September 2026). (City of Virginia Beach — Planning Department, Development Services Center open data, via BidBro's Permit Pulse)
  • Building permits (structural work, which goes through plan review) took longer than trade permits: median 2 days, a quarter took 10 days or more, the slowest tenth 26 days or more (17,263 applications, residential and commercial).
  • 1,796 residential permits in BidBro's record for Virginia Beach fall into 12 project types; the most common are electrical panel / service upgrade (274), swimming pool (245), home addition (212). (public permit records linked to directory contractors)
  • Virginia DPOR lists 2,242 contractor licences based in Virginia Beach: 1,349 Class A, 343 Class B, 550 Class C. (DPOR regulant lists, September 29, 2026)
  • Building permits in Virginia are issued under the Uniform Statewide Building Code; the city administers it and the contractor normally applies for the permit as part of the job.

As of . Cite as: BidBro, “Virginia Beach building permits: what needs one, how long it takes, how to check one,” https://www.bidbro.com/guides/virginia-beach-building-permits.

Which work carries a permit in Virginia Beach: what the record shows

Each row is a kind of residential work that appears on Virginia Beach building permits filed by contractors in BidBro’s directory, with the job value the contractor declared to the city. If your project is on this list, expect a permit; the city’s permit office (linked below) makes the final call on anything not listed.

Project typePermitsMedian declared valuePeriod
Electrical panel / service upgrade274$2,500February 2020 – July 2024
Swimming pool245$39,000January 2020 – August 2024
Home addition212$50,000January 2020 – June 2024
Re-roof or roof repair180$6,500January 2020 – July 2024
HVAC installation (new system or ductwork)171$7,500February 2020 – July 2024
Water heater replacement168$1,500February 2020 – July 2024
Deck build, rebuild or repair116$10,000January 2020 – July 2024
New single-family home99$250,000January 2020 – June 2024
Kitchen remodel89$12,000February 2020 – July 2024
HVAC system replacement87$10,000April 2020 – June 2024
Standby generator83$3,900February 2020 – July 2024
Bathroom remodel72$10,000February 2020 – July 2024

These are the permits linked to contractors in BidBro’s directory, as collected from public permit records by a third-party aggregator that keeps roughly the 20 most recent per contractor — not every permit the city issued. Project types with fewer than 30 permits are not listed (roof and siding: 3, siding replacement: 8, solar: 14). Full method: Virginia Beach home project costs from building permits.

How long a building permit takes in Virginia Beach

Virginia Beach publishes every permit application with the date it was filed and the date it was issued. BidBro’s Virginia Beach Permit Pulse measures the days between the two on 104,888 applications filed January 2023 – September 2026. Most residential trade permits are issued the same day or the next; structural building permits, which go through plan review, take longer.

Days from application to issue, by permit type (residential and commercial permits).

Permit typeApplicationsMedianA quarter took at leastSlowest tenth took at least
Building17,2632 days10 days26 days
Electrical15,0351 day3 days7 days
Mechanical13,6321 day4 days8 days
Plumbing9,9541 day2 days6 days
Gas5,3121 day3 days8 days
Roof and/or siding1,2363 days7 days14 days

Calendar days from the application date to the issue date the city recorded; nearest-rank percentiles; applications never issued are excluded. In 2026 so far, residential applications ran at a median of 1 day and a slowest tenth of 11 days or more. Source: City of Virginia Beach — Planning Department, Development Services Center, “Building Permits Applications”. Look up the current wait for your permit type with the permit wait-time tool.

How the permit process works in Virginia Beach

  1. Confirm the work needs a permit. Structural work, additions, decks, pools, re-roofs, and new or replaced electrical, plumbing, gas and mechanical equipment are permitted in Virginia Beach. If the work is on the table above, plan for a permit; for anything else, ask the Permits & Inspections Division before you start.
  2. The contractor applies. A licensed contractor normally files the application under its DPOR licence and lists the declared value of the work. Electrical, plumbing, mechanical and gas work each get their own trade permit alongside, or instead of, a building permit.
  3. Plan review, when drawings are needed. Additions, new homes, structural changes and pools go through plan review (and zoning review for setbacks and lot coverage) before the permit is issued. This is why building permits take longer than trade permits in the table above.
  4. The permit is issued. The permit card is posted at the job. Work that needs a permit should not start before it is issued.
  5. Inspections as the work proceeds. The contractor requests inspections at the stages the permit lists (footings, framing, rough-in, final). An inspector from the city signs off each stage.
  6. Final inspection closes the permit. A passed final inspection closes the permit. Keep the record: a buyer, an insurer or a lender may ask for it.

How to check a permit

Virginia Beach publishes its building-permit applications as open data (the "Building Permits Applications" dataset on the city's open-data portal), which shows each permit's type, status, application date and issue date. The Permits & Inspections Division can confirm a permit and its inspections by address.

On BidBro, a contractor profile shows the building permits linked to that business in the public record, so you can see what kind of work a firm has pulled permits for before you hire it.

The official offices

Links checked by BidBro’s Hampton Roads permit source directory, last verified October 11, 2026.

The licence behind the permit

In Virginia the contractor who pulls a permit for paid work must hold a Board for Contractors licence of the right class for the contract value: Class C under $30,000 per job, Class B from $30,000 to under $150,000, Class A above that (Code of Virginia § 54.1-1100). 2,242 such licences are based in Virginia Beach (DPOR, September 29, 2026). Every class and specialty code is decoded in Virginia contractor licence classes, explained; check a specific business at DPOR’s licence lookup.

Questions Virginia Beach homeowners ask about permits

How long does a building permit take in Virginia Beach?

Usually a day or two. On the city's own records the median from application to issue was 1 day for residential work, and nine in ten were issued within 12 days. Building permits that need plan review are slower — median 2 days, with the slowest tenth taking 26 days or more. Electrical, plumbing, mechanical and gas permits had a median of 1 day.

Do I need a permit to replace a roof in Virginia Beach?

Virginia Beach issues permits for re-roofing: BidBro's record holds 180 re-roof or roof-repair permits, declared at a median of $6,500. The city's roof-and-siding permits were issued in a median of 3 days, nine in ten within 14 days. Your roofer should pull it; ask to see the permit card before the tear-off starts.

Do I need a permit to build a deck in Virginia Beach?

Decks are permitted work in Virginia Beach: the record holds 116 deck permits (build, rebuild or repair), declared at a median of $10,000. A deck is structural, so expect plan review and footing and framing inspections; very small, low, free-standing platforms may not need one — ask the Permits & Inspections Division.

Does replacing an HVAC system or water heater need a permit?

Yes — equipment replacement is permitted as mechanical or plumbing work. The record holds 87 HVAC system replacements (median $10,000) and 168 water heater replacements (median $1,500). Trade permits like these were issued in a median of 1 day.

How long does a pool permit take in Virginia Beach?

A pool needs a building permit with plan and zoning review plus electrical work, so it follows the slower building-permit track (median 2 days, a quarter 10 days or more). The record holds 245 pool permits declared at a median of $39,000.

Who pulls the permit — me or the contractor?

For paid work, the contractor normally does, under its Virginia DPOR licence, and the permit fee is usually in the quote. A contractor who suggests skipping the permit is asking you to carry the risk: unpermitted work can fail a home sale inspection or an insurance claim.

How can I look up a building permit in Virginia Beach?

Search the city's "Building Permits Applications" open dataset by address, or ask the Permits & Inspections Division. BidBro contractor profiles also list the permits linked to each business in the public record. The issue-time figures on this page come from BidBro's Permit Pulse release, which reads the same city dataset.

Plan the project around the permit