Calendar days from application to issue, by permit type · applications 2023-01-01 to 2026-08-21 · release 1.1.0
| Permit type | Median | Slowest quarter | Slowest tenth | Permits |
|---|---|---|---|---|
| Building | 2 days | 10 days | 26 days | 16,963 |
| Electrical | 1 day | 3 days | 7 days | 14,830 |
| Mechanical | 1 day | 4 days | 8 days | 13,388 |
| Plumbing | 1 day | 2 days | 6 days | 9,792 |
| Gas | 1 day | 3 days | 9 days | 5,240 |
| Elevator | 8 days | 14 days | 24 days | 209 |
Calendar days from the application date the city recorded to the issue date the city recorded, computed by BidBro from the City of Virginia Beach's published Building Permits Applications records. This is permit review time only — not construction time, and not total project time. It makes no claim about why any figure is what it is. Addresses, permit numbers, parcels and applicants are never requested or published.
The data made available here has been modified for use from its original source, which is the City of Virginia Beach. Neither the City of Virginia Beach nor the Office of the Chief Information Officer (CIO) makes any claims as to the completeness, timeliness, accuracy or content of any data contained in this application; makes any representation of any kind, including, but not limited to, warranty of the accuracy or fitness for a particular use; nor are any such warranties to be implied or inferred with respect to the information or data furnished herein. The data is subject to change as modifications and updates are complete. It is understood that the information contained in the web feed is being used at one’s own risk.